Receiving a shipment, resolving a discrepancy and authorizing an insulator for installation are different steps. This guide helps procurement, quality and site teams keep a traceable record between delivery and the project’s installation decision. It does not specify how to lift, clean, test or install a unit, and it does not replace the manufacturer's instructions for the exact design or the project's safety procedures.
Match the shipment to the approved design
Start with the approved product code, drawing revision, order line, shipment list and package identifiers. Check that the documents and labels refer to the same offered design, including its end fittings where relevant. Keep the actual receipt count separate from the expected count. If an identification mark or revision is unclear, record the difference and request clarification rather than assigning a similar product code yourself.
Preserve a usable receiving record
For each discrepancy, record the affected package or unit, date, quantity and location. Where permitted, keep a photograph of the label, packaging and observed condition before the record is lost through unpacking or movement. Distinguish an observed mark from an engineering finding: a photograph can support follow-up, but cannot establish the internal condition or prove electrical conformity. Follow the agreed project process for inspection, evidence and notification.
Obtain the actual product instructions
Ask for the current instructions applicable to the supplied model and identify their revision in the handover record. Confirm which packaging, storage, transport and handling requirements apply before work is planned. Do not transfer a different manufacturer's instructions, a porcelain or glass product procedure, or a generic value to the received composite design. If the required document is missing, list it as unresolved and refer the decision to the responsible project party.
Keep a suspected discrepancy separate from release
| State | Record | Next decision |
|---|---|---|
| Received; records match | Order line, identifiers, quantity, observed condition, applicable instruction revision | Continue through the project’s agreed inspection and authorization steps; receipt alone is not release. |
| Identity or document unclear | Conflicting labels or versions, affected quantity, question and responsible party | Obtain a traceable clarification for the exact item before treating it as the approved design. |
| Suspected damage or other exception | Affected units, package and photos, current control status and related evidence | Refer to the manufacturer and authorized project personnel under the agreed process. Do not infer that an unapproved repair or visual recheck makes it fit for installation. |
| Disposition agreed | Written decision, scope, conditions, responsible person and evidence of implementation | Close only the covered items after required checks; keep any remaining exceptions visible. |
Hand over the record before installation
The handover should connect the approved design and instruction revision to the quantities, identified units, open exceptions and written disposition. State who can release the units and which checks remain. Do not treat a supplier reply, delivery signature or a complete spreadsheet as installation authorization. Where the project requires inspection or testing, use its agreed procedure and authorized personnel.
Background reading: EPRI composite insulator research and the CIGRE TB 184 public summary. These sources identify the handling issue; this checklist does not reproduce their procedures.