Home › Technical Center › Composite Insulator Receiving and Handover
Procurement Checklist 4 min read Updated

Composite Suspension Insulators: Receiving Records and Pre-installation Handover

Match the delivered design, document exceptions and keep receipt separate from installation authorization.

Technical Reference Download PDF Datasheet

Receiving a shipment, resolving a discrepancy and authorizing an insulator for installation are different steps. This guide helps procurement, quality and site teams keep a traceable record between delivery and the project’s installation decision. It does not specify how to lift, clean, test or install a unit, and it does not replace the manufacturer's instructions for the exact design or the project's safety procedures.

Match the shipment to the approved design

Start with the approved product code, drawing revision, order line, shipment list and package identifiers. Check that the documents and labels refer to the same offered design, including its end fittings where relevant. Keep the actual receipt count separate from the expected count. If an identification mark or revision is unclear, record the difference and request clarification rather than assigning a similar product code yourself.

Preserve a usable receiving record

For each discrepancy, record the affected package or unit, date, quantity and location. Where permitted, keep a photograph of the label, packaging and observed condition before the record is lost through unpacking or movement. Distinguish an observed mark from an engineering finding: a photograph can support follow-up, but cannot establish the internal condition or prove electrical conformity. Follow the agreed project process for inspection, evidence and notification.

Obtain the actual product instructions

Ask for the current instructions applicable to the supplied model and identify their revision in the handover record. Confirm which packaging, storage, transport and handling requirements apply before work is planned. Do not transfer a different manufacturer's instructions, a porcelain or glass product procedure, or a generic value to the received composite design. If the required document is missing, list it as unresolved and refer the decision to the responsible project party.

Keep a suspected discrepancy separate from release

Receiving status and next decision
StateRecordNext decision
Received; records matchOrder line, identifiers, quantity, observed condition, applicable instruction revisionContinue through the project’s agreed inspection and authorization steps; receipt alone is not release.
Identity or document unclearConflicting labels or versions, affected quantity, question and responsible partyObtain a traceable clarification for the exact item before treating it as the approved design.
Suspected damage or other exceptionAffected units, package and photos, current control status and related evidenceRefer to the manufacturer and authorized project personnel under the agreed process. Do not infer that an unapproved repair or visual recheck makes it fit for installation.
Disposition agreedWritten decision, scope, conditions, responsible person and evidence of implementationClose only the covered items after required checks; keep any remaining exceptions visible.

Hand over the record before installation

The handover should connect the approved design and instruction revision to the quantities, identified units, open exceptions and written disposition. State who can release the units and which checks remain. Do not treat a supplier reply, delivery signature or a complete spreadsheet as installation authorization. Where the project requires inspection or testing, use its agreed procedure and authorized personnel.

Background reading: EPRI composite insulator research and the CIGRE TB 184 public summary. These sources identify the handling issue; this checklist does not reproduce their procedures.

Frequently Asked Questions

Receiving and Handover FAQs

No. Receipt observations are part of the record; required acceptance decisions and tests follow the project’s agreed procedure.

Request the current instructions applicable to the exact supplied model and approved design, including the requirements relevant to storage and movement before installation.

The responsible project personnel and manufacturer review the identified unit and evidence under the agreed procedure. Record their written disposition and its scope; do not self-release it.

No. It is a documentation and communication checklist, not a handling, inspection, testing or installation instruction.

Before Installation Handover

Review the Handover Scope

Send the offered model, drawing revision, applicable instructions and affected quantities for scope review. Document availability and next steps depend on the actual product and project requirements.